COMPLETED
November 2024 - Aside from a few small punch list items, this project is now complete. The Town will look to add landscaping to this area in an overall redevelopment of the parking lot in 2025/2026. The Town will seek public input on what they wish to see in this parking lot and then, with the help of a landscape architect, design it and build it to meet the needs of the community.
August 21, 2024 - The Town learned today that the kiosk is complete, but the contractor is waiting on the “Welcome to Essex, NY lettering to arrive. Once that arrives, it will be affixed to the kiosk and will be installed onto the concrete pad. The Town will host a grand unveiling of this project once it is installed and completed.
June 28, 2024 - Progress is being made as site work prep takes place. The pouring of concrete is slated to take place on July 1.
May 22, 2024 - At their May 2024 board meeting, the Town Council selected John W. Sheehan and Sons, Inc of Willsboro to construct the kiosk and foundational pad at a total amount not to exceed $28,440.000.
April 16, 2024 - Interested bidders for this project may refer to these plans for complete details and technical drawings. Site plans that explain how this project will comply with NYS DOT setback regulations can be found here. Questions may be referred to Supervisor Ken Hughes or kiosk designer Mark Hall of Hall Design Group (email is best).
Project outcome: The construction of a kiosk with appropriate paving for accessibility and structural support on the south side of the parking lot entrance across from the Essex Ferry dock to display an historic timeline.
Cost: $28,440.00
Funding Sources: Essex County Community Enhancement Funds
Worked performed by: John W. Sheehan and Sons, Inc.
Timeline: June/July 2024